Seismic Conditions vs. Material Handling System: What You Should Know

Greg Conner | 21 November 2012

 

Have you ever heard someone say, “It’s just rack," or how about, “It's only ceiling hung conveyor.”? Anyone who has been in the material handling industry could tell you that it ain’t just rack and you better think before hanging anything on the ceiling.

Planning for your racking and ceiling hung conveyor projects is a critical first step no matter what, but never more important than when installing them in areas where seismic events can occur. Below are some items to discuss prior to budgeting for your facility layout when seismic conditions and related permits are key factors to a successful project... Consider the subsequent list as the fundamentals for determining a seismic pallet rack job:

  • Slab thickness and whether or not the slab is reinforced
  • Soil compaction underneath the slab
  • Seismic zone in which the building is located
  • Code requirements of the city: UBC (uniform building code) or IBC (international building code)
  • Rack layout and profile design
  • Number of beam levels and the unsupported length; the greater the distance, the less the frame will be able to handle (this is very important when considering an alteration to existing pallet rack)
  • Structural or roll formed, and if the rack is bolted, snap together, or welded

Consider the subsequent list as the fundamentals for determining a ceiling hung conveyor job:

  • Building construction at the customer’s facility: spec building or custom build?
  • Seismic zone in which the building is located
  • Code requirements of the city
  • Types of conveyor to be used (weight)
    • Consider the drive locations
    • Consider whether or not you can common support
  • Ceiling joist orientation and the type of header steel you can use (usually C4 is the most common – anything larger will require a special U-Bolt; you can always opt for a double C4 if a structural engineer deems a C6 or similar is required). This is very important because your project costs can skyrocket if you don’t research ahead of time.

Once you have considered some of the criteria for the project, you will need to find an engineering firm that is licensed in the state where the job is to be installed. After you find a firm, a professional engineer will perform detailed seismic and load calculations and drawings. Assuming everything you have proposed is satisfactory, the engineer will stamp the calculations and drawings (some municipalities require copies of your stamped calculations and drawings). Here are some other tricky items to consider if you wish to avoid potential show stoppers:

  • Have the firm you plan on hiring conduct preliminary calculations based on your design; preliminary calculations are often done at no charge!
  • Consider OSHA or other regulations
  • Local fire department (a lot of rules are subjective when it comes to fire codes; they vary depending on interpretation of the code)
  • Allow plenty of time to obtain the necessary permits; cities have the right to shut down your job if you don’t have the proper paper work. Often times a project may be at the mercy of a city engineer’s approval.

The reality is most cities and municipalities are requiring permits and seismic rated and stamped calculations/drawings. Allowing the proper time to develop the design criteria and obtain approval from the city are an absolute must. Lastly, the firm you hire to complete your calculations and stamp your drawings may have knowledge on the city you plan to install your project; leverage on their experience. Good Luck!

Author: Greg Conner

Greg is the SVP of Corporate Development and Marketing at Bastian Solutions. A proud Purdue University graduate, at Bastian he works to identify and drive strategies to propel the company forward. His responsibilities include identification of emerging technologies, forming strategic partnerships and M&A activities and execution of the strategic planning process. He carries with him years of experience in the field, having previously worked as a project engineer, field application engineer and regional director of Indiana. 

Comments

SPS Chauhan says:
8/28/2018 10:08 AM

Nice insight on the Siesmic Considerations

Leave a Reply

Your email address will not be published.

 

Thank you for your comment.

Rate this Blog Post:

Spell Check

Archives

Latest Case Study

 

20220224-DENSO-Toyota-Core-tow-tractor-tugger-agv-autonomous-vehicle-automotive-distribution-loading-pallet-transfer-cart_3

Denso

Learn how AGVs helped Denso achieve a 48% reduction in process defects and 33% reallocated labor to better positions with no eliminated roles. 

 

Close